In Lagos, property developers must navigate a strict approval process enforced by multiple agencies and laws. Key stakeholders include the Lagos State Ministry of Physical Planning & Urban Development (via LASPPPA—Lagos State Physical Planning Permit Authority), the Lands Bureau (which issues statutory land titles), the Lagos State Building Control Agency (LASBCA), and the Lagos State Real Estate Regulatory Authority (LASRERA).
Lagos laws (Urban & Regional Planning Law Cap. U2 and related regulations) require a registered Certificate of Occupancy (CoO) or Governor’s consent, or as applicable, before final permits are granted. LASRERA oversees developers’ licensing and transaction standards. In practice, the building approval process has two main stages: a provisional planning permit (if the title isn’t yet registered) and a final planning permit (once the title is secured).
“Provisional Planning Permit” refers to the temporary permit granted to applicants before the issuance of the final permit. This could be granted to applications before they obtain the registered Certificate of Occupancy or consent, or ratification, as applicable.
Building Approval Processes
Suppose Ola is the developer.
Throughout, Ola consults licensed architects, surveyors, and engineers (professionals registered under Lagos law) and ensures all submissions meet the Lagos Physical Planning & Development Regulations. He also registers his project with LASRERA, which “supervises applications for permits…not limited to project development,” ensuring compliance with developer regulations.
Provisional vs Final Planning Permits
Lagos defines a Provisional Planning Permit as a “temporary permit granted to applicants before the issuance of the final permit,” specifically when they have not yet obtained the registered CoO or consent. In other words, if Ola only has a letter of allocation or proof of pending title, LASPPPA may still start the approval process.
The proviso is that the developer must produce the registered title within a set timeframe. Until recently, Lagos allowed up to 18–24 months (two years) for this, but reforms in 2021 drastically shortened it. The state reduced the window from two years to nine months for converting provisional to final approvals.
If Ola’s provisional permit expires without finalization, Lagos law treats it as invalid. In late 2021, the State published lists of expired provisional permits and warned that such permits “ceased being tenable for building construction.” Owners with expired permits were given only one month to apply for final permits before enforcement (such as permit revocation or demolition) began.
In Ola’s case, once he presents the CoO to LASPPPA within the allowed period, he is issued the final planning permit. This final permit must be visibly displayed on-site during construction.
After approval, Ola notifies the Lagos State Building Control Agency before breaking ground. This triggers stage inspections (foundations, roofing, utilities, etc.) to ensure compliance with the Lagos Building Code.
Under the Regulation, no building may be occupied without first obtaining a Certificate of Completion and Fitness for Habitation from LASBCA. In practice, LASBCA inspects the finished structure and issues this certificate (also called a Certificate of Fitness).
If Ola or any owner ignores these rules, the consequences are severe. Lagos law voids any planning permit granted if conditions aren’t met and empowers LASBCA to pull down non-compliant buildings at the owner’s expense. For example, after construction, Ola must obtain LASBCA’s Fitness certificate before sales or occupancy; violating this risks demolition.
Learning from Lagos Demolition Cases
Lagos’s enforcement has been dramatic in recent years, underscoring the importance of compliance. In the Oworonshoki floodplains (September 2025), dozens of unapproved buildings were demolished.
Authorities emphasized that an earlier amnesty (May–Dec 2024) had given owners ample time to regularize their permits. Only a handful applied, and the Lagos State Building Control Agency said most structures “were distressed, blocking drainage,” and unsafe.
The Permanent Secretary noted that due process was followed—all owners were notified and given amnesty opportunities—before carrying out the demolition. This case illustrates that illegal or unapproved construction (even in sprawling informal estates) will not be tolerated, especially in hazard-prone areas.
Another lesson came from the Trade Fair Complex (Ojo) controversy (October 2025). Some traders argued the federally owned site should be exempt from Lagos approval. Lagos replied firmly that state law still applies: a Supreme Court ruling (2003) confirmed that physical planning is concurrent, so even federal lands fall under Lagos’s jurisdiction for planning permits.
The Commissioner for Physical Planning stated the Trade Fair Management Board “does not have powers to approve…developments independent of Lagos State,” and any construction there “requires a Lagos State planning permit” or it is illegal. This sparked a brief standoff, but Lagos ultimately demolished unpermitted structures, underscoring that no developer (federal or private) can bypass Lagos rules.
These cases reinforce key points: always secure statutory land title and obtain state permits at every stage. Unapproved buildings—whether in a slum or a trade center—risk being razed.
Best Practices & Takeaways
By following Lagos’s laws—securing title, obtaining both provisional and final permits from LASPPPA, and completing LASBCA inspections—developers like Ola can build confidently.
These steps, grounded in Lagos’s Physical Planning and Building Control Regulations, protect property value and safety. Ignoring them risks project delays, financial loss, or even demolition. Stakeholders must thus stay informed and work with licensed professionals to meet all requirements.
Overview of the 2025 Tenancy & Recovery Bill The Lagos State House of Assembly introduced…
Nigeria’s housing crisis is vast: estimates of the national deficit range from 20 to 28…
The 2021–2025 cycle reshaped the legal perimeter of Nigerian real estate. At the federal level,…
Kenya’s real estate market has expanded steadily over the last five years, recording an estimated…
Inflation is not an abstract index; it is the silent tax that devalues effort. Technically,…
Africa Sustainable placemaking discussions at the 2025 API Summit At the Africa Property Investment (API)…